Build Session 17

January 10, 2015

A group photo at the end of the day.
700_6412

Another step closer to walking (pun intended). Cole implemented proportional speed control of the pneumatic cylinders in an attempt to avoid overshoot:
DSC_0553
and Ed sewed the elastic straps used to connect the slide potentiometers to the wearer:
DSC_0552
Cole then sewed the straps onto the potentiometers:
700_6434

The test was MUCH better than last week, but there is still quite a bit of refinement to do.

The other main activity today was preparing for the Kickstarter campaign. Thelonius started setting up our Kickstarter project page, including backer levels and gifts:
DSC_0551
Joseph and Gabriel worked on the script for the Kickstarter video, and once the shooting was done Joseph began the editing process:
700_6435

Next week we’ll work on completing the Kickstarter project, and we’ll tweak the control aspects of walking.